Resolution11-1013Adopted
Dept/ Agency: Water & Sewer Utilities Action: ( ) Ratifying (X) Authorizing (X) Amending Type of Service: Change Order # 1/Amend Resolution # 7R12-b 070109 Purpose: Decrease the contract amount and extend the contract completion time by 47 days for the Phase VI(C) Sewer Rehabilitation Entity Name: Spiniello Companies Entity Address: 354 Eisenhower Parkway, Livingston, NJ 07039 Decrease Contract Amount: $1,112,653.50 New Contract Amount: $4,882,521.50 Funding Source: City of Newark Budget/ Water & Sewer Utilities Contract Period: 290 calendar days from notice to proceed, extended by 47 calendar days Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: N/A
Progress
✓
Introduced
Sep 26, 2011
✓
In Committee
Oct 5, 2011
✓
Passed
Oct 5, 2011
4
Enacted