All Legislation
Resolution12-2245Filed

Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Bid Contract Purpose: Hank Aaron Park-Site Improvements Basketball Courts Entity Name: Berto Construction Inc. Entity Address: 625 Leesville Avenue, Rahway, New Jersey 07065 Contract Amount: $111,460.00 Funding Source: City of Newark Budget/Engineering Contract Period: One (1) year from the issuance of a Notice to Proceed Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS ( X ) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Additional Information: Bids Solicited: 2 Bids Received: 1 Bids Rejected: 1 Bids Re-Solicited: 10 Bids Received: 3 Bids Rejected: 0 Contract #10-2012(R)

Progress

Introduced

Nov 19, 2012

In Committee

Feb 6, 2013

Passed

Feb 6, 2013

4

Enacted