All Legislation
Resolution16-0056Filed
Dept/ Agency: Engineering Action: ( ) Ratifying (X) Authorizing ( X ) Amending Type of Service: Professional Services Contract Purpose: McClellan Street Underpass Roadway and Drainage Improvements Final Design, Change Order No. 3 Entity Name: Parsons Brinckerhoff, Inc. Entity Address: 2 Gateway Center, 18th Floor, Suite 1803, Newark, New Jersey 07102 Contract Amount: $0.00 Funding Source: N/A Contract Period: Extend the contract period through February 1, 2017 Contract Basis: ( ) Bid ( ) State Vendor ( X ) Prof. Ser. ( ) EUS ( ) Fair & Open ( X ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) n/a Addition Information: Original contract amount of $1,091,849.92 and termination date of January 15, 2014. Change Orders No. 2 & 3 extended termination dates by one year each, with no increase in contract amount.
Progress
✓
Introduced
Jan 12, 2016
✓
In Committee
Mar 2, 2016
✓
Passed
Mar 2, 2016
4
Enacted