Resolution18-0299Adopted
Dept/ Agency: Water and Sewer Utilities Action: ( ) Ratifying (X) Authorizing ( ) Amending Type of Service: Change Order No. 01/Amend Resolution 7R12-e June 21, 2017 Purpose: Execute Change Order No. 01 for Queen Ditch Restoration Project Contract 04-WS2013 Entity Name: Rencor Inc. Entity Address: 24 Tannery Road, Somerville, New Jersey 08876 Contract Amount: Original Contract Amount: $4,502,557.00 unchanged, Increase in contract time by 114 additional calendar days Funding Source: Water and Sewer Utilities Capital Budget Contract Period: 240 Calendar Days to Final Completion extended by 114 days Contract Basis: (X) Bid ( ) State Vendor ( ) Prof. Ser. ( ) EUS (X) Fair & Open ( ) No Reportable Contributions ( ) RFP ( ) RFQ ( ) Private Sale ( ) Grant ( ) Sub-recipient ( ) N/A Additional Information: Change Order No. 01 extending completion time by 114 calendar days.
Progress
✓
Introduced
Feb 28, 2018
✓
In Committee
Mar 21, 2018
✓
Passed
Mar 27, 2018
4
Enacted