Resolution2026-0752Reported from Standing Committee
Resolution providing for a supplemental agreement or agreements with Michael Baker International, Inc. for costs associated with the construction phase of the Charles Anderson Bridge Project; providing for the payment of the costs thereof, not to exceed Four Million Seventy-Seven Thousand Six Hundred Eighty-Seven Dollars and Forty Cents ($4,077,687.40), an increase of Two Hundred Fifty Thousand Eight Hundred Thirty-Seven Dollars and Forty-Seven Cents ($250,837.47) from the previously legislated contract authorization, reimbursable at 100%.
Progress
✓
Introduced
Jul 17, 2026
✓
In Committee
Jul 21, 2026
3
Passed
4
Enacted