All Legislation
Ordinance1657-2026Passed
To authorize the Director of the Department of Public Utilities to modify and increase the contract with Black & Veatch Corporation for the Lower Olentangy Tunnel - Phase 1 project; to authorize the Director of Public Utilities to submit the Lower Olentangy Tunnel - Phase 1 contract modification for loan funding and to execute any paperwork necessary to accept loan funding for this project; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; to amend the 2025 Capital Improvement Budget; to appropriate funds within the Water Pollution Control Loan Fund; and to authorize an expenditure of up to $1,084,736.71 from the Water Pollution Control Loan Fund to pay for the project. ($1,084,736.71)
Progress
✓
Introduced
May 27, 2026
✓
In Committee
Jun 30, 2026
✓
Passed
Jul 2, 2026
4
Enacted